Citation. 22 Ill.64 F.2d 344 (2d Cir. 1933)
Law Students: Don’t know your Studybuddy Pro login? Register here
Brief Fact Summary.
Plaintiff used a bid submitted by Defendant, in creating a bid. Plaintiff seeks to enforce Defendant’s bid.
Synopsis of Rule of Law.
A general contractor cannot enforce a bid made by a subcontractor as a bilateral contract when the general contractor is under no obligation to use the subcontractor’s bid if awarded the job and the general contractor did not accept the subcontractor’s bid before it was revoked. A general contractor is also unable to enforce the subcontractor’s bid based on promissory estoppel when there is no consideration
Facts.
Plaintiff received a bid from Defendant for supplying linoleum needed in the construction of a public building. Plaintiff used Defendant’s bid in computing the bid submitted to the public authorities. Defendant realized that a mistake had been made in computing the amount of linoleum needed and that the job would require a greater amount. The public authorities accepted Plaintiff’s bid. Plaintiff received Defendant’s written confirmation of withdrawal the day after the public authorities accepted Plaintiff’s bid.
Issue.
Can Plaintiff enforce Defendant’s bid?
Can Plaintiff enforce Defendant’s bid as a contract?
Can Plaintiff enforce Defendant’s bid under the doctrine of promissory estoppel?
Held.
No. Plaintiff cannot enforce Defendant’s bid under either theory.
A contract is not automatically formed when a general contractor uses the bid of a subcontractor in creating a bid, even if that bid results in the general contractor being awarded the job. A bilateral contract is not formed because the general contractor is not required to use the subcontractor if awarded the job.
In addition, a contract was not formed between the general contractor and the subcontractor under these facts because the general contractor did not accept the subcontractors bid before it was revoked.
The Court rejects Plaintiff’s promissory estoppel claim based on a lack of consideration.
The Court also reasons that this is not an option contract because enforcing the subcontractor’s bid as an option contract would require the subcontractor to keep the offer open, but the general contractor would not be required to purchase from the subcontractor. Although not mentioned by the Court, another reason this is not an option contract is lack of consideration.
Discussion.
A general contractor cannot enforce a subcontractor’s bid when the general contractor is not required to use the subcontractor if the job is awarded and the subcontractor’s bid is revoked before the general contractor accepted.
This Court does not allow the general contractor to enforce the subcontractor’s bid using promissory estoppel. The Court does not allow the Plaintiff to recover under promissory estoppel where there is no consideration. The Court’s holding on the promissory estoppel claim may be explained in part by the limited use of promissory estoppel at the time of the decision (1933).